Moranbah North Mine - Dam 6 Civil Works and CDA North Expansion Works

  • Location - Moranbah, QLD
  • Value - $27M
  • Start date - Jun 2021
  • Completion date - Jun 2022
  • Client - Anglo American

SEE Civil were first engaged by Anglo American in June 2019 on the Three Chain Road and Dawson Highway Upgrade near Moura in Central QLD.

Due to our collaborative nature and safety record on site, we were awarded another two contracts in quick succession by Anglo American, totaling $67M.

The Moranbah North Mine – Dam 6 and Co-Disposal Area Northern Expansion Civil Works project is the third project Anglo American have awarded to SEE Civil. The project commenced in June 2021 and is expected to be complete in June 2022.

Scope of works

Dam 6 Civil Works

  • 52ha clearing and grubbing
  • 392,256m3 topsoil removal
  • 532,853m3 dam embankment cut to fill
  • 9,275m3 pavement materials,
  • Decant structure, valves, and fitting
  • Return water inlet structure
  • Geotechnical vibrating wire piezos

Co-disposal Area Northern Expansion Civil Works

  • 161ha clearing and grubbing
  • 340,300m3 topsoil removal
  • 898,220m3 CDA embankment cut to fill
  • Decant structures
  • Decant outlet pipes
  • Geotechnical vibrating wire piezos