[PROJECTS]

Kingscliff
Foreshore Works

Client

Tweed Shire Council

Location

Kingscliffe, New South Wales

Value

$14.1m

Duration

February 2017 – March 2018

Status

Complete

The revitalisation of the Kingscliff foreshore brings the protection of the foreshore, the creation of a central park with active and passive space, and modernisation of a key tourism asset, the Kingscliff Beach Holiday Park.

Works included:

  • rock armour and concrete seawall (including piling) foreshore protection works
  • associated construction and landscaping works for the creation of the new Kingscliff Central Park and viewing platforms
  • associated construction and landscaping works for the upgrade of the Kingscliff Beach Holiday Park including all civil infrastructure.
Project Scope

  • Demolition of existing holiday park and infrastructure
  • Excavate 35,000m3 for revetment walls
  • Supply and place 47,000 tonnes of Rock Revetment Wall including temporary sheet piling and de-watering
  • Management of 2,600 truck movements for rock supply
  • Install 270 CFA (Continuous Flight Auger) concrete piles for the concrete seawall
  • Form and pour 450m3 of marine environment reinforced concrete for sea wall
  • Utility works – stormwater, water, sewer and electrical
  • Earthworks and pavements to complete Holiday Park and Central Park
  • Extensive landscaping works for Central Park and the Holiday Park
  • Highly environmentally sensitive site on Kingscliff Beach
  • Detailed stakeholder engagement as the project is centrally located to shops, tourist destinations and clubs.
Earthworks

The Kingscliff foreshore project was situated within a tidal zone, necessitating the constant use of temporary enclosures and dewatering to facilitate ongoing construction activities. To create the necessary construction zones, temporary embankments were erected using sheet piling. Notably, both the revetment wall and the concrete step structure were located within a 2-meter proximity of the tidal area.

Rock Protection and Ground Retention

  • Typical Revetment Detail section showing a three-layer rock system within 2m of a tidal zone. Rock protection varied from 320mm nominal diameter to 1480mm diameter depending on the layer. Each layer had to be specifically picked and placed in order to ensure that there would be adequate protection within the tidal zone. The rock protection area covered a total of 365 LM, with approximately 1400t of sub-layer (D50=0.32m), 14,200t of secondary layer (D50=0.69m) and 26,800t of primary layer rock (D50=1.48m) placed over the length of the sea wall.
  • The project contained a total of 277 permanent piles. These included a breakdown of the following:
    • Soft Secant piles: 115 no. off x 500Dia x 5.5 – 10.2m deep
    • Hard Secant piles: 118 no. off x 500D x 5.5 – 10.2m deep
    • Pile-Support piles: 44 no. off x 500-600Dia x 5.07 -11.2m deep
Stakeholder Engagement

The project was centrally located within the Kingscliff township, surrounded by key establishments such as a Surf Club, Bowling Club, and a variety of businesses, including accommodation resorts, restaurants, cafes, a hotel, a chemist, and numerous others.

To ensure the effective engagement of project stakeholders, a transparent and open approach to communication was established with the Council, the Kingscliff Chamber of Commerce, and other relevant parties to ensure local businesses were kept up to date with project works and minimise disruption to businesses.

Additionally, the project had to navigate the challenge of coping with a significant flow of pedestrians in close proximity to the construction site.

Work With Us.

Mountain

WE PRIDE OURSELVES ON THE KNOWLEDGE, SKILLS AND EXPERIENCE OF OUR PEOPLE.

 

SEE Group builds teams and workplaces where everyone can be their best.