[PROJECTS]
Working airside and within the constraints of an operational airport had been a challenge. The project was successfully completed just in time for this taxiway to be an option for aircraft-carrying visitors, officials, and athletes for the Gold Coast 2018 Commonwealth Games. Improved operational efficiency and increased aircraft taxi routing options have been delivered by this project.
SEE Civil had worked with the client to re-program the works schedule so the new taxiway was commissioned and operational prior to peak travel periods during the 2018 Gold Coast Commonwealth Games, at no additional cost to the client.
Works were constructed in an operational airside environment (including night works and runway/taxiway closures) to construct 450 meters of new Code E taxiway pavement at Gold Coast Airport, linking two existing taxiways. Works also included asphalt overlay and strengthening of four other existing taxiways.
WE PRIDE OURSELVES ON THE KNOWLEDGE, SKILLS AND EXPERIENCE OF OUR PEOPLE.
SEE Group builds teams and workplaces where everyone can be their best.