[PROJECTS]

Gold Coast Airport Northern
Apron Overlay and Taxiway Echo Widening

Client

Gold Coast Airport

Location

Gold Coast, Queensland

Value

$9.2m

Duration

August 2014 – May 2015

Status

Complete

The project was for the construction of a new Taxiway Echo adjacent to airport parking bays, including drainage works, subgrade treatment, and asphalt finishing works.

The Northern Apron works required the installation of new Joint User Hydrant Infrastructure (JUHI) fuel lines and valve pits including resurfacing the existing international airplane parking bays.

Additional works were required for geotechnical testing of the airfield runway which required highly programmed night works to ensure all works were complete for the airfield to be operational the following morning.

Project Scope

  • Echo Taxiway required cement and lime stabilisation to the subgrade.
  • Careful management of pavement placement and works due to an elevated water table sitting at a subgrade level.
  • Installation of stormwater drainage and HumeCeptors.
  • Installation of fuel mains, hydrants and valves
  • Pavement works.
  • Concrete stormwater drain construction.
  • Electrical works, including erection of new lighting towers and modifications to existing.
  • Asphalt pavement and line-marking.